The night time restrictions should last until approximately August 12th.
In the area from 97th to 77th the restrictions will be from 7:00 pm to 6:00 am.
In the area from north of 77th to north of US 30 restrictions will be from 9:00 pm to 6:00 am.
The intersection of US 231 and US 41 will be done at night instead of during the day due to the traffic load. The contractor anticipates this to take 3 nights from July 5th thru July 7th. After the Intersection of US 231 and US 41 is complete the contractor will move North to the intersection of US 30 and US 41. This will take approximately 5 nights to do some more partial depth patching due to the condition of the existing asphalt.
After the completion of the partial depth patching the contractor will move back down to the intersection of 97th and US 41 and work their way north milling the existing asphalt surface and paving back the new asphalt surface.